Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

Chapter 5 - Estimating Project Times and Costs

Multiple Choice Questions

1.The process of forecasting or approximating the time and cost of completing project

deliverables is called

A. Budgetin

g.

B. Predictin

g.

C. Estimatin

g.

D. Plannin

g.

E. Guesstimatin

g.

2.In practice, estimating processes are frequently classified as

A. Top down/bottom

up.

B. Rough/polishe

d.

C. Precise/order of

magnitude.

D. Draft/fin

al.

E. Broad/Specifi

c.

3. What is the relationship between organizational culture and estimating?

A. There is no

relationship

B. Cultural norms affect the accuracy of

estimates

C. Culture determines whether estimates are

made

D. Estimating alters cultural

norms

E. Estimating and culture are

independent

4.A good starting point for developing time and cost estimates is

A. Past

experience.

B. Work

packages.

C. Task

analysis.

D. Time and motion

studies.

E. Work breakdown

structure.

Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

What is a Work Breakdown Structure?

Free 30-day WBS Software Trial

Breaking work into smaller tasks is a common productivity technique used to make the work more manageable and approachable. For projects, the Work Breakdown Structure (WBS) is the tool that utilizes this technique and is one of the most important project management documents. It singlehandedly integrates scope, cost and schedule baselines ensuring that project plans are in alignment.

The Project Management Institute (PMI) Project Management Book of Knowledge (PMBOK) defines the Work Breakdown Structure as a “deliverable oriented hierarchical decomposition of the work to be executed by the project team.” There are two types of WBS: 1) Deliverable-Based and 2) Phase-Based. The most common and preferred approach is the Deliverable-Based approach. The main difference between the two approaches are the Elements identified in the first Level of the WBS.

Deliverable-Based Work Breakdown Structure

A Deliverable-Based Work Breakdown Structure clearly demonstrates the relationship between the project deliverables (i.e., products, services or results) and the scope (i.e., work to be executed). Figure 1 is an example of a Deliverable-Based WBS for building a house. Figure 2 is an example of a Phase-Based WBS for the same project.

Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

Figure 1 – Deliverable Based Work Breakdown Structure

In Figure 1, the Level 1 Elements are summary deliverable descriptions. The Level 2 Elements in each Leg of the WBS are all the unique deliverables required to create the respective Level 1 deliverable.

Phase-Based Work Breakdown Structure

In Figure 2, a Phase-Based WBS, the Level 1 has five Elements. Each of these Elements are typical phases of a project. The Level 2 Elements are the unique deliverables in each phase. Regardless of the type of WBS, the lower Level Elements are all deliverables. Notice that Elements in different Legs have the same name. A Phase-Based WBS requires work associated with multiple elements be divided into the work unique to each Level 1 Element. A WBS Dictionary is created to describe the work in each Element.

Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

Figure 2 - Phase Based Work Breakdown Structure

A good WBS is simply one that makes the project more manageable. Every project is different; every project manager is different and every WBS is different. So, the right WBS is the one that best answers the question, “What structure makes the project more manageable?”.

How to Make a Work Breakdown Structure

A good Work Breakdown Structure is created using an iterative process by following these steps and meeting these guidelines:

  1. Gather Critical Documents
    1. Gather critical project documents.
    2. Identify content containing project deliverables, such as the Project Charter, Scope Statement and Project Management Plan (PMP) subsidiary plans.
  2. Identify Key Team Members
    1. Identify the appropriate project team members.
    2. Analyze the documents and identify the deliverables.
  3. Define Level 1 Elements
    1. Define the Level 1 Elements. Level 1 Elements are summary deliverable descriptions that must capture 100% of the project scope.
    2. Verify 100% of scope is captured. This requirement is commonly referred to as the 100% Rule.
  4. Decompose (Breakdown) Elements
    1. Begin the process of breaking the Level 1 deliverables into unique lower Level deliverables. This “breaking down” technique is called Decomposition.
    2. Continue breaking down the work until the work covered in each Element is managed by a single individual or organization. Ensure that all Elements are mutually exclusive.
    3. Ask the question, would any additional decomposition make the project more manageable? If the answer is “no”, the WBS is done.
  5. Create WBS Dictionary
    1. Define the content of the WBS Dictionary. The WBS Dictionary is a narrative description of the work covered in each Element in the WBS. The lowest Level Elements in the WBS are called Work Packages.
    2. Create the WBS Dictionary descriptions at the Work Package Level with detail enough to ensure that 100% of the project scope is covered. The descriptions should include information such as, boundaries, milestones, risks, owner, costs, etc.
  6. Create Gantt Chart Schedule
    1. Decompose the Work Packages to activities as appropriate.
    2. Export or enter the Work Breakdown Structure into a Gantt chart for further scheduling and project tracking.

Caution: It is possible to break the work down too much. How much is too much? Since cost and schedule data collection, analysis and reporting are connected to the WBS, a very detailed WBS could require a significant amount of unnecessary effort to manage.

There are many WBS software tools available. Some of them are based on mind mapping and others are drawing tools. You can read about these tools in this WBS software review.

Here is an example of how to make a WBS with MindView:

How to Use a Work Breakdown Structure

The Work Breakdown Structure is used for many different things. Initially, it serves as a planning tool to help the project team plan, define and organize scope with deliverables. The WBS is also used as the primary source of schedule and cost estimate activities. But, its biggest contributions to a project are is use as a description all of the work and as a monitoring and controlling tool.

Work Packages
Figure 3 shows the House Project Work Breakdown Structure expanded to Level 1, 2, and 3 Elements. The lowest Levels of each Leg and Branch of the WBS are called Work Packages. Work Packages cover information related to the deliverable, such as owner, milestones, durations, resources, risks, etc. This information is described in the WBS Dictionary.

Planning Packages
There is another type of Work Package called a Planning Package. When the project management plan is approved, scope is known, but not necessarily all of the details. In order to apply the 100% Rule and capture all of the scope, Planning Packages are created. It is understood that as details are defined, the Planning Packages eventually evolve to Work Packages. In the House Project, the project manager knows that the house will have fixtures, but at the time construction begins, there is only a fixture allowance and no fixtures identified. Once the fixtures are determined, the associated Planning Package becomes a Work Package. This planning process is call Rolling Wave Planning and is a from of Progressive Elaboration.

Which of the following is not one of the recommended guidelines for developing useful work packages estimates?

Figure 3 – WBS Work Packages and Control Accounts

Control Accounts
The other application of the WBS is as a monitoring and controlling tool. This is accomplished by defining Control Accounts. Control Accounts are WBS Elements at which the project plans to monitor and report performance. The Control Accounts can be any Element in the WBS. In the House Project, the project manager decides that the project risks associated with using subcontractors can be better managed if the project reports performance for each subcontractor. To monitor their performance, Elements 3.1, 3.2 and 3.3 have been identified as Control Accounts. However, the remaining work in Elements 1.0 and 2.0 will be performed by company resources with less risk and the project does not feel like monitoring and controlling is needed at lower Levels. To assist with the monitoring and reporting, project management information tools are used to collect, analyze and report information at any Element within the WBS.

Create a WBS with the MindView software free trial. Check it out.

Related Links:

Option d is the correct answer. Contingency is an event or situation or activity that may or may not occur in the future. Hence, the level of contingency is not recommended in the guidelines of package estimates. Option a. It is an incorrect option because estimations of packages should be made in relation to the work.

Which of the following is a good condition for top

Answer and Explanation: The good condition for top-down estimating is when the project is small and internal.

What is included in work package in project management?

A work package is a group of related tasks within a project. Because they look like projects themselves, they are often thought of as sub-projects within a larger project. Work packages are the smallest unit of work that a project can be broken down into when creating your Work Breakdown Structure (WBS).

What information is included in a work package?

Just like a project, your work package will include all elements, such as a budget, material(s), human resources, and schedules and milestones.